Find

Crosstown Water Main Project

Upcoming Construction for the Week of May 23 – May 27

  • Bike path excavations and grading north of Half Day Road continues this week. Once completed, crews will begin paving and patching the new path.

  • This project was originally anticipated to be completed in May; however, due to increased rainfall, it is now anticipated to be completed in mid-June, weather permitting.
  • Path users are encouraged to use the path detours highlighted below:

Crosstown Bike Path Alternate Route May 2022

Construction Completed During the Week of May 16 – May 20

  • All construction and restoration work along Riverwoods Road, south of Half Day Road, was completed.

  • Crews performed earth excavations and began bike path grading on the west side of Riverwoods Road, north of Half Day Road.

 

Surrey Lane Drainage Project

Upcoming Construction for the Week May 23 – May 27

  • The contractor will continue troubleshooting and resolving any underground utility conflicts and installing new piping and structures.

  • This project is anticipated to be completed in mid-June, weather permitting.

 

Construction Completed During the Week of May 16 – May 20

  • New pipes and structures were installed on the south side of Surrey Lane, near where the storm sewer system will discharge storm water.

  • Utility conflicts were encountered which slowed progress the rest of the week.Surrey Lane Drainage Project May 2022

Sign up HERE to get Construction E-Mail Updates