Menu

Lincolnshire Drive South Drainage Improvement Project 

Where – Lincolnshire Drive, Wiltshire Drive, Londonderry Lane

  • What – Drainage, watermain, and pavement improvements on Lincolnshire Drive and Wiltshire Drive 

When – March - November 

*Refuse pickup will begin at 6 a.m. on Lincolnshire Drive and Wiltshire Drive during project.

LEAF COLLECTION UPDATE:
As the fall season begins, the Village is working with LRS on a plan to collect leaves from residents impacted by the Lincolnshire Drive South Drainage Improvement project. The curbside leaf collection program does not begin until the week of October 19.

In the coming weeks, residents are asked not to place leaves in the parkway to allow construction crews unhindered access to the parkway areas as they work on getting the final sections of curb installed, utility structures adjusted, and final layers of asphalt placed.

Detailed leaf pickup instructions will be distributed to all impacted residents on Lincolnshire Drive and Wiltshire Drive in the coming weeks. If you have specific concerns regarding leaf collection, please contact Public Works at 847-913-2380.

2026 0929 LRS Leaf

Contract Completion Date – May 2027 

Construction Completed: September 21 – September 25

  • Waterproofing and backfilling for the lower portion of the pump station. 

  • All water services and final water main connection on Wiltshire Drive. 

  • Continued structure adjustments along Lincolnshire Drive between Londonderry Lane and Wiltshire Drive. 

  • Curb, gutter, and concrete driveways poured along Lincolnshire Drive from Wiltshire Drive to the northern limit.

Construction Planned: September 28 – October 2

  • Removal of the pump station’s temporary soil retention system. 

  • Layout for curb and gutter along Wiltshire Drive. 

  • Curb framing and pouring anticipated this week. 

  • Fine grading for binder course along Lincolnshire Drive from Wiltshire Drive to the northern limit.

2026 0908 Lincolnshire Dr Drainage1

Crews Slip Forming New Concrete Curb On Lincolnshire Drive

2026 0929 Lincolnshire Dr Drainage2

Newly completed concrete driveway apron

2026 0929 Lincolnshire Dr Drainage3

Excavation for new water service being bored under Wiltshire Drive

 The Village appreciates everyone’s patience during the project.

For a more detailed description of the project, view the Village’s interactive map.

If you have questions or concerns about this project, contact: 

  1. Adam Harn – 815-973-8446 – Ciorba Group Resident Engineer 

  2. Michael Kowalski – 773-355-2954 – Ciorba Group Project Manager  

  3. Village Engineer Wally Dittrich – 847-913-2387 –   

  4. Lincolnshire Public Works – 847-913-2380  

  5. For after-hours concerns (weekends or weekdays after 3 p.m.), call the Police non-emergency number at 847-883-9900.


Sorry, this website uses features that your browser doesn’t support. Upgrade to a newer version of Firefox, Chrome, Safari, or Edge and you’ll be all set.